Key Details
MoSPI’s October 2026 Monthly Flash Report tracks ongoing Central Sector infrastructure projects costing ₹150 crore or more through PAIMANA-PROJ. Its totals describe the projects under monitoring at month-end.
Indicator | September 2026 | October 2026 |
|---|---|---|
Projects monitored | 1,853 | 1,862 |
Latest estimated project cost | ₹37.56 lakh crore | ₹38.11 lakh crore |
Cumulative expenditure | ₹17.73 lakh crore | ₹17.87 lakh crore |
Expenditure as a share of latest cost | 47.21% | 46.88% |
Projects above 80% physical progress | 654 | 649 |
Projects above 80% financial progress | 338 | 326 |
During October, 38 projects were added to monitoring. The portfolio total nevertheless increased by nine; the two figures describe different things.
Transport and Energy Remain the Largest Part of the Portfolio
Transport and logistics accounted for 1,324 projects worth ₹20.37 lakh crore, while energy accounted for 229 projects worth ₹11.31 lakh crore. Together they represented 83.4% of monitored projects and about 83.1% of their latest estimated cost. The project-number share is unchanged from September, making it an important feature of the portfolio rather than a new shift in October.
Roads and highways made up most transport projects. Within energy, the report covered oil and gas, electricity generation, transmission and distribution, and storage. Spending as a share of latest estimated cost differed across these activities: it stood at 50.64% for transport and logistics and 39.49% for energy. These are expenditure measures, not percentages of infrastructure completed.
October Added Projects and Recorded Commissioning
Of the 38 projects newly added to PAIMANA monitoring, 23 came from the Ministry of Road Transport and Highways. The additions include a proposed highway connection to Vadhavan Port and two phases of the Ahmedabad Metro.
MoSPI also reports that a ₹4,445-crore transmission scheme connecting renewable-energy zones in Koppal and Gadag, Karnataka, was commissioned on 16 October. The release lists rebuilding of coke-oven batteries at Bhilai Steel Plant as another October commissioning. Its list additionally includes an NH-66 corridor commissioned in July 2025, which should not be counted as an October completion.
Portfolio Totals Cannot Show How Each Project Advanced
Cumulative expenditure rose by ₹0.14 lakh crore between the September and October reports, while the latest estimated cost of projects under monitoring rose by ₹0.55 lakh crore. Consequently, the aggregate expenditure-to-cost ratio edged down from 47.21% to 46.88%. That movement does not mean work already done was reversed: projects can enter or leave the monitored set, and their latest estimated costs can change.
October’s counts of projects above 80% physical progress and 80% financial progress were also lower than September’s. They are separate measures and do not identify whether the same projects are in both groups. Assessing delivery requires following individual projects through construction, spending and commissioning, not treating changes in portfolio-wide counts as project-level progress.
What Is PAIMANA-PROJ?
PAIMANA-PROJ is MoSPI’s interface for monitoring reported progress on Central Sector infrastructure projects costing at least ₹150 crore. Its underlying PAIMANA-CRIP repository collects project information from implementing ministries and departments. The flash report covers selected infrastructure categories; it is not a count of all infrastructure projects or investment in India.
Policy Relevance
The October report gives implementing ministries a current view of a ₹38.11-lakh-crore monitored pipeline, with oversight particularly consequential for roads, railways and energy. The commissioning of the Karnataka transmission scheme also shows why a completed asset is a more concrete delivery milestone than expenditure alone.
For judging whether implementation is improving, the useful comparison is project by project: changes in estimated cost, physical progress, spending and commissioning dates. The October and September totals provide context, but the changing composition of the monitored portfolio limits what can be inferred from their differences.
Follow the Full Press Release Here: MoSPI’s October 2026 Monthly Flash Report on Central Sector Infrastructure Projects.