Green Hydrogen Supply Commitments Reach 5.56 Lakh Tonnes a Year, with Most Earmarked for Export

Indian companies have signed 23 offtake agreements since 2023, including 18 in 2026 - commitments could support projects requiring over ₹90,000 crore in investment, but most of that capacity has yet to be built

Policy Bites image

Key Details

Under the National Green Hydrogen Mission (NGHM), Indian companies are securing buyers for green hydrogen and products made from it, including green ammonia and methanol. The latest agreements cover future supply, while the mission’s 2030 target and commissioned capacity show how much production still needs to be developed.

Measure

Reported Position

Signed offtake agreements

23 contracts covering 5,55,610 tonnes a year of green-hydrogen-equivalent supply through October 2026

Agreements signed in 2026

18, covering more than 4 lakh tonnes a year of hydrogen-equivalent supply

Export share

More than 70% of the contracted quantity is earmarked for exports

Investment

Projects fulfilling the agreements are expected to require over ₹90,000 crore; this is not investment already realised

Commissioned capacity

About 8,000 tonnes a year of green hydrogen capacity had been commissioned by February 2026, according to the earlier backgrounder

NGHM target

At least 5 million tonnes a year of production capacity by 2030

The contracted quantity is expressed as green-hydrogen equivalent because agreements also cover products made from hydrogen, such as green ammonia and methanol. Their stated product tonnages should not be added directly to the hydrogen-equivalent total.


Export Agreements Give Proposed Projects a Market

An offtake agreement sets out a buyer’s commitment to purchase future output. The newly reported contracts therefore provide a potential market for Indian producers, particularly in Japan and Europe, but deliveries depend on plants being built and meeting the agreements’ terms. The release cites green-ammonia supply arrangements with Japanese and German buyers, with some deliveries expected to begin in 2029.

MNRE describes India’s signed commitments as the world’s largest. That is a claim about contracted future supply, not current production or exports. The distance between reported offtake and commissioned capacity shows the scale of construction and financing still required.

Domestic Fertiliser and Refinery Demand Is Developing Alongside Exports

The NGHM is also supporting domestic demand in industries that already use hydrogen. Under its Strategic Interventions for Green Hydrogen Transition (SIGHT) Programme, agreements have been signed for the production and supply of 6,70,000 tonnes a year of green ammonia to 11 fertiliser units. Projects have separately been awarded to supply 30,000 tonnes a year of green hydrogen to refineries.

These figures describe different products and programme arrangements, so they should not be combined with the 5,55,610-tonne hydrogen-equivalent offtake figure. Replacing fossil-based hydrogen in fertiliser production and refining is one route to lowering industrial emissions; exports are another potential market.

Production Support Now Has to Translate into Operating Capacity

The NGHM combines production incentives with support for domestic electrolyser manufacturing, pilots, hydrogen hubs and certification. The earlier government backgrounder reports incentives awarded for 8,62,000 tonnes a year of green hydrogen production capacity and for 3,000 MW a year of electrolyser manufacturing capacity. Awards are a step towards production, not evidence that those capacities are operating.

Certification will also matter for export sales. India has notified standards for green hydrogen and its derivatives and established a certification scheme to verify whether products meet the relevant emissions requirements.


Policy Relevance

The new contracts strengthen the demand case for investment under the NGHM. Their value as an industrial milestone will depend on whether producers can secure renewable electricity, finance and infrastructure, commission plants on schedule, and deliver certified products at competitive prices. Tracking commissioned capacity and actual deliveries alongside agreements will make progress easier to judge.

The balance between export orders and domestic use also matters. Fertiliser plants and refineries offer opportunities to replace fossil-based hydrogen within India, while overseas contracts may help proposed plants achieve scale. The policy test is whether both markets develop without treating expected investment or contracted supply as realised output.


Relevant Question for Policy Stakeholders: As signed orders grow, which constraints most need to be resolved for Indian plants to begin certified deliveries to export buyers and domestic industrial users?


Follow the Full Press Releases Here: Green Hydrogen Offtake Commitments, 29 October 2026 | Green Hydrogen Mission Backgrounder, 28 October 2026

Rethinking Public Policy Through Insight | Inquiry | Impact

Opinion • Grassroots Voices • Policymakers Perspectives • Expert Analysis • Policy Briefs