Key Details
India’s wind sector has gained momentum, while the distance between installed capacity and its expansion ambitions makes project delivery the next test.
Measure | Position |
|---|---|
Installed wind capacity | 59.20 GW as of 30 September 2026, up from 21 GW in March 2014 |
Latest annual addition | 6.05 GW in 2025–26, the highest recorded in a financial year |
Projects under implementation | 28 GW |
Stated expansion ambitions | 100 GW by 2030 and 156 GW by 2036 |
Domestic turbine manufacturing capacity | About 24 GW as of March 2026, up from 10 GW in 2014 |
Offshore wind support | ₹6,853 crore in approved viability-gap funding for 1 GW of projects off Gujarat and Tamil Nadu |
Record Additions Still Leave a Delivery Gap
Wind capacity has grown nearly 2.8-fold since March 2014, and the 6.05 GW added in 2025–26 exceeded the previous annual record of 5.4 GW in 2016–17. Wind generated 106.7 billion units of electricity in 2025–26. It accounted for about one-fifth of India’s 299.25 GW installed renewable energy capacity at the end of September 2026.
The stated 100 GW ambition for 2030 is roughly 41 GW above September’s installed capacity. The 28 GW under implementation represents a substantial pipeline, but those projects will contribute to electricity supply as they are completed and connected to the grid.
Wind’s Value Extends Beyond Capacity
Wind and solar power generate electricity at different times. The government says nearly 45% of wind generation occurs during peak-demand hours, making wind a useful complement to solar in a renewable-heavy power system. Hybrid projects, storage-linked supply and better forecasting can help make that combination more dependable.
India has substantial assessed wind resources, particularly in Rajasthan, Gujarat, Maharashtra and Karnataka. The estimate of 1,163.9 GW at a height of 150 metres describes gross resource potential — rather than capacity already built or immediately available for development. Suitable sites still require land access, transmission connections and viable projects.
Manufacturing and Offshore Projects Shape the Next Phase
Domestic wind-turbine manufacturing capacity reached about 24 GW by March 2026, with the government reporting 70–80% indigenisation across key components. This gives expansion an industrial dimension alongside its electricity-system role.
Offshore wind remains at an earlier stage. Approved viability-gap funding covers 500 MW each off Gujarat and Tamil Nadu. A separate 500 MW pilot using a contract-for-difference mechanism is intended to give developers greater revenue certainty. These measures seek to establish projects and supporting infrastructure; they are distinct from the installed onshore capacity reported above.
Policy Relevance
The immediate question is whether record annual additions can be sustained and increased. The Ministry’s January 2026 task force is addressing land, regulatory, transmission and implementation constraints—issues that will determine how quickly the project pipeline becomes operating capacity.
Wind’s contribution should also be judged by when and where it delivers electricity, not capacity alone. Transmission expansion, forecasting, storage and coordination with solar projects will affect its usefulness during peak demand. At the same time, offshore projects will test whether public support can help establish a commercially workable new segment.
Relevant Question for Policy Stakeholders: Which land, transmission and project-execution constraints most threaten completion of the 28 GW wind pipeline, and how will progress against them be measured?
Follow the Full Update Here: India’s Wind Energy Transition: Charting Path towards 156 GW and Beyond