Renewable Power Is Outpacing the Grid: India Faces Connection Delays and Unused Generation

An IRENA–CREEI report cites expected grid-connection delays for about 20 GW of Indian solar and wind projectsand at least 2.3 TWh of renewable electricity curtailed in 2025. It argues that transmission capacity, ways to balance supply and demand, and grid stability must develop together if new renewable plants are to deliver reliable power

Reports/Data Releases image

Key Details

Solutions for Building a New Power System: The Role of Grids, Storage and Hydropower, by the International Renewable Energy Agency (IRENA) and China Renewable Energy Engineering Institute (CREEI), examines what electricity systems need as solar and wind generation expands. Its India figures illustrate the wider problem: building generation capacity does not ensure that the electricity can reach users when needed.

Measure

Report’s Finding

India’s project connections

About 20 GW of solar and wind projects are expected to face average grid-connectivity delays of four to five months beyond commissioning timelines.

India’s unused renewable power

At least 2.3 TWh was curtailed in 2025 and 300 GWh in the first quarter of 2026 because of transmission constraints, according to estimates cited by the report.

Global grid investment

IRENA estimates annual investment needs rising from about US$0.5 trillion in 2025 to US$1 trillion a year during 2026–2035.

India’s transmission model

The report highlights competitively awarded projects in which private firms build and operate transmission assets and receive long-term payments linked to availability and performance.


New Renewable Plants Need Grid Connections at the Right Time

Solar and wind projects can be completed faster than major transmission lines. When their schedules diverge, a finished plant may wait to connect, or available electricity may go unused because the grid cannot carry it. The report uses India’s expected connection delays and reported curtailment to show why generation and transmission need to be planned as one system.

Expanding the grid remains essential, but the report also examines ways to use existing lines more effectively. These include technologies that assess how much electricity a line can safely carry under current conditions and equipment that directs flows around congested parts of the network.

Storage and Hydropower Help Move Electricity Across Time

A grid with more solar and wind must respond to changes in generation across the day and over longer periods. Batteries, pumped hydropower, other hydropower plants and flexible electricity demand can help match supply with consumption. They serve different needs: a battery may respond rapidly to a shortfall, while hydropower or other resources may provide flexibility for longer.

The report’s example from China shows the value of coordinating assets. Joint operation of the Lianghekou hydropower station and nearby Kela solar plant enabled use of 99% of the solar output and increased utilisation of their shared transmission corridor by around 20%. It is a case study of what coordinated operation can achieve, rather than a forecast for other countries.

A Reliable Grid Also Needs New Stability Services

Conventional power plants have traditionally helped maintain the grid’s frequency and voltage. As more electricity comes from solar and wind equipment connected through inverters, system operators need other ways to provide those stability services. The report discusses approaches including grid-forming inverters, synchronous condensers and changes to operating rules. Its point is that capacity, flexibility and stability are connected requirements: progress on one cannot fully compensate for a shortage of another.


Policy Relevance

The immediate issue is the timing and usefulness of investment for India. Better alignment between renewable-project commissioning and transmission completion could reduce connection waits and curtailment. Making more effective use of existing lines could also provide relief while new infrastructure is built.

The report’s Indian transmission example shows one route for attracting private capital: payments tied to an asset’s availability and performance, rather than the volume of electricity flowing through it. As storage and other flexible resources grow, planning and market rules will also matter because they determine whether these resources can provide— and be paid for — the services the grid needs.

The figures establish where pressure is emerging; future evidence on connection times and grid reliability would better show whether system investment is keeping pace with renewable capacity.


Follow the Full Report Here: Solutions for Building a New Power System: The Role of Grids, Storage and Hydropower