Key Details
The Flash Report covers ongoing Central Sector infrastructure projects costing ₹150 crore or more. By July 2026, cumulative expenditure had reached ₹19.26 lakh crore, equivalent to 51.91% of the revised project cost.
Scale: The portfolio comprises 735 mega projects costing at least ₹1,000 crore and 1,040 major projects in the ₹150–1,000 crore range.
Cost revision: Their combined original cost was ₹33.70 lakh crore. The revised estimate of ₹37.11 lakh crore represents an increase of approximately 10.1%.
Physical progress: 675 projects, or around 38%, had crossed 80% physical completion.
Financial progress: 305 projects, or around 17%, had incurred more than 80% of their revised cost.
New monitoring coverage: Another 36 projects were added to the platform in July, including telecommunications, steel, roads, power and urban infrastructure projects.
Transport Dominates the Investment Pipeline
Transport and logistics account for 1,246 projects—70% of the total—and ₹19.81 lakh crore, or 53% of the revised cost. This category includes roads, railways, aviation, urban transport, ports and inland waterways.
Energy is the second-largest component, with 205 projects worth ₹10.66 lakh crore. The remaining investment is distributed across water and sanitation, communications, social and commercial infrastructure, and sectors such as coal, steel and mining.
At the ministry level:
The Ministry of Road Transport and Highways has 993 projects worth ₹9.62 lakh crore.
Railways has 190 projects worth ₹6.38 lakh crore.
The Power Ministry has 98 projects carrying a comparatively high revised cost of ₹6.08 lakh crore.
Petroleum and natural gas projects account for another ₹4.23 lakh crore.
The figures show that the Centre’s monitored infrastructure pipeline remains heavily concentrated in connectivity and energy, which together account for 82% of its revised cost.
Project Progress Is Concentrated at Both Ends
The report identifies sizeable groups of projects at the initial and advanced stages. This reflects new projects entering the pipeline alongside older projects approaching completion.
Physical and financial progress need not move identically: expenditure may be incurred early for land, equipment or mobilisation, while some payments follow completed construction. Nevertheless, the difference between projects crossing 80% physical completion and those crossing 80% financial completion makes project-level monitoring more useful than the aggregate expenditure figure alone.
Among the projects commissioned during July were the Srikakulam–Angul gas pipeline, packages of the Aligarh–Kanpur and Dwarka expressways, and a transmission system linked to renewable-energy evacuation from Gujarat’s Khavda region.
What Is PAIMANA?
PAIMANA-PROJ is MoSPI’s monitoring platform for large Central Sector infrastructure projects. It consolidates information on project costs, expenditure and implementation progress across ministries.
Its supporting repository, PAIMANA-CRIP, was launched in July 2026 to standardise infrastructure data. Nearly 80% of its information is updated through application programming interfaces (APIs), reducing dependence on separate manual submissions and enabling more regular project tracking.
Policy Relevance
Revised costs need project-level explanation. The portfolio’s approximately 10% increase over original estimates may reflect changes in scope, input costs, land acquisition or implementation delays. The release does not disaggregate these causes.
Sectoral concentration creates shared risks. With transport and energy accounting for most monitored investment, delays in clearances, land acquisition, equipment supply or financing in these sectors could have an outsized effect on the overall infrastructure programme.
Progress should be assessed against timelines as well as expenditure. A project can record substantial spending without remaining on schedule or delivering its intended service. Monitoring should connect physical and financial progress with original completion dates, revised deadlines and reasons for delay.
The new repository could improve accountability. Standardised, API-based reporting can help ministries identify stalled projects earlier, provided the underlying data remain timely, comparable and open to scrutiny.
Follow the Full Update Here: Flash Report on Central Sector Infrastructure Projects, July 2026

