Haryana to Gain Additional Yamuna Water as Six States Advance Kishau Multipurpose Project

The inter-state MoU on the Kishau project resolves key issues related to water and power sharing and allows the long-pending project to move towards implementation

Policy Bites image

Key Details

  • Inter-State Agreement: Six states have signed an MoU to advance the Kishau Multipurpose Project after reaching consensus on key issues, including water and power sharing.

  • Haryana’s Yamuna Share: Haryana states that it has a 48% share in Yamuna waters, making additional water availability from the project directly relevant to the State.

  • Three-Project Strategy: Kishau is being considered alongside the Renuka Ji and Lakhwar projects, both of which are already under construction.

  • Expected Haryana Allocation: According to the State government, Haryana’s combined share from the three projects will be around 1,143 million cubic metres (MCM).

  • Additional Water Availability: The three projects are expected to collectively add around 2,676 cusecs, of which Haryana’s stated share would be approximately 1,280 cusecs.

  • Implementation Stage: The MoU removes an important inter-state hurdle, but the Kishau project is not yet operational; construction is expected to move forward after the remaining implementation processes.


The MoU Resolves a Major Inter-State Coordination Barrier

The six-state agreement on the Kishau Multipurpose Project marks an important institutional step in moving forward a project that had remained pending because of unresolved inter-state issues,  including the sharing of water and power. For Haryana, the principal benefit is expected to come from increased availability of Yamuna water, alongside supplies anticipated from the Renuka Ji and Lakhwar projects.

Large river projects involving several states often require agreement not only on water allocation but also on power benefits, costs and implementation responsibilities. The latest agreement therefore provides the institutional basis for moving the project beyond prolonged negotiations.

For Haryana, the project is especially significant because any increase in regulated Yamuna water availability can support its future water requirements.


Haryana’s Benefit Is Linked to the Wider Upper Yamuna Storage System

For Haryana, Kishau forms part of a broader strategy involving the Renuka Ji, Lakhwar and Kishau projects.

Together, these projects are intended to increase regulated water availability in the Yamuna system. According to the Haryana government, the State’s combined entitlement from the three projects would be around 1,143 MCM, equivalent to an additional share of about 1,280 cusecs.

The significance is not only the volume of water created, but the ability of storage projects to make supplies more reliable across seasons.


Agreement Does Not Yet Mean Immediate Water Availability

The MoU is an important enabling step, but its practical impact will depend on the pace of project execution.

For Kishau, the next phase will involve translating the inter-state agreement into construction, financing and operational arrangements. The eventual water benefit will therefore depend on:

  • timely project implementation;

  • completion of associated infrastructure;

  • adherence to agreed water-sharing arrangements; and

  • coordination among participating states and central agencies.

The policy significance lies in moving the project from an inter-state negotiation problem towards an implementation challenge.


Policy Relevance

  • Inter-state consensus reduces a major implementation barrier: Agreement on water and power sharing can help unlock projects delayed by competing state interests.

  • Storage capacity can strengthen dry-season water availability: Regulated releases can improve reliability compared with dependence only on seasonal river flows.

  • The three projects should be assessed together: Kishau, Renuka Ji and Lakhwar collectively form a larger water-security strategy for the Yamuna basin.

  • Execution will now become the critical issue: Financing, construction timelines and coordination will determine when additional water actually becomes available.

  • Allocation alone will not resolve water stress: Haryana will still need efficient distribution, conservation and demand management to maximise the benefit of additional supplies.


Relevant Question for Policy Stakeholders: What institutional mechanism should oversee the three projects collectively to ensure that agreed water allocations translate into reliable and timely supplies for participating states?


Follow the Full News Here: Haryana to Gain Additional Yamuna Water as Six States Advance Kishau Multipurpose Project 